Sponsored
News

You’re Economical With The Truth, Oyo State Govt Tells Fashola

Sponsored
Sponsored

 

The Oyo State Government has reacted to a claim by the Federal Minister of Works and Housing, Babatunde Raji Fashola (SAN), that it is responsible for the non-completion of the Lagos-Ibadan Expressway project, saying he is economical with the truth.

In a statement signed by the Commissioner for Information, Culture and Tourism, Dr. Wasiu Olatubosun, on Monday, the Oyo State Government said it is imperative to set records straight as a government committed to ensuring that the good people of Oyo State enjoy the dividends of good governance.

The statement read:

Firstly, we need to clarify that two major projects, the dualization of the 8.2km Agodi – Gate – Old Ife – Adegbayi Junction Road and a few projects under the World Bank assisted Ibadan Urban Flood Management Project (IUFMP) interface with the 127.6 km Lagos-Ibadan Expressway project at CH 115-117, CH 117 and CH 125. In real terms, this stretch is less than 3 kilometers.

Secondly, we would have expected that the Federal Ministry of Works and Housing would have reached out to us to find out how long we would need to complete the aforementioned projects being that Oyo State has been in communication with the Ministry. In fact, just about a year ago, we had requested permission from the Federal Ministry of Works and Housing (through the Director of Federal Highways) to dualize the underpass at CH 115 -117. We were advised to make sure that the diversion routes are completed before embarking on the diversion. We complied 100%.

Also, it is on record that the majority of the 22km stretch of the Lagos -Ibadan Express Road between the old Tollgate Ibadan – Ojoo is still work in progress. Earthwork between Iwo Road Interchange and Ojoo has only just commenced. While work between the Old Ibadan Tollgate and Onipepeye is still in progress and characterized by road diversions. With all this work yet to be done, why is the Federal Minister blaming the Oyo State Government for delaying the project?

Had the Federal Minister reached out to the Oyo State Government, we would have told him that although the contract for work on the dualization of Agodi-Gate- Old-Ife Road – Adegbayi Junction which includes an underpass interface with the Lagos Ibadan Expressway at Onipepeye had to be terminated at 60% in September 2022 due to slow pace of work by the contractor, whose contract was awarded under the previous administration, the Oyo State Government is in the process of re-awarding the remaining 40% with a February 2023 delivery date. We have also provided 500m diversions of the main expressway lanes from the impacted site to allow traffic flow on both sides. Similarly, the IUFMP projects also have 4-month completion schedules.

Given that the pace of work on the Lagos-Ibadan Expressway has been at 10/km per year (it has taken almost 10 years since 2013 for work so far done on the 127.6km stretch of road to be completed), it could take about 2 years to finish the work and get to CH 127.6. Why then will our projects with 4-month remaining be the source of delay of completion of the project?

One would also wonder why it was okay to skip the Lagos end of this project between Berger and Old Lagos Tollgate and the about 2 km stretch between Shagamu and Ogere, but it suddenly becomes impossible to skip the less than 3km CH 115-117 and 125 and continue work on the remainder 22km.

From all of the above, it is clear that the Federal Minister did not have the right facts right in ascribing blame for non-completion of the Lagos Ibadan Express Road to the Oyo State Government. Even after the less than 3km CH 115-117 and 125 is completed in February 2023, we doubt if the Lagos-Ibadan Expressway project would be anywhere near completion to CH127.6.

Sponsored
Alinnor Arinze

Recent Posts

Team Nigeria Takes Care of Business, With Weightlifting Gold Sweep and Sprint Surge on Day 4

AFOLABI SAHEED OLAWALE  Team Nigeria continued its outstanding campaign at the 2026 Commonwealth Games on…

31 minutes ago

Information Minister, Idris, Hails NTA’s New World Class Studio, Upgrade of National Press Centre

The Honourable Minister of Information and National Orientation, Mohammed Idris, has expressed satisfaction with the…

56 minutes ago

How Nigeria’s Banking Sector Can Maximise the Benefits of Recapitalisation

HENRY OBIEKA Nigeria's banking industry is entering one of the most significant transformation periods since…

2 hours ago

Africa Is Filled With Untapped Talents Waiting To Flourish –Awele Elumelu

Chairperson of Transcorp Hotels Plc, Avon Healthcare Limited and Heirs Insurance Brokers, Dr. Awele Elumelu,…

3 hours ago

Former Tottenham Coach Unveils Bold Vision to Transform Nigerian Football

England-based Nigerian coach Demi Emmanuel Olutoge has unveiled an ambitious blueprint aimed at transforming Nigerian…

4 hours ago

Abuja Electricity Rewards 1,126 Employees with Promotions and Step Increments

Abuja Electricity Distribution Plc (AEDC) has announced the promotion of 547 employees and the approval…

6 hours ago
Sponsored