Ikeja Electric Announces 132KV Lines Upgrade, As Parts Of Lagos May Experience Outage

Posted on October 4, 2021

Ikeja Electric (IE), Nigeria’s largest Electricity Distribution company has announced the planned re-conductoring of 132KV lines embarked upon by the Transmission Company of Nigeria (TCN), aimed at expanding the capacity to wheel more power.

The Chief Technical Officer, Ikeja Electric (IE), Jide Kumapayi, who disclosed this while addressing journalists, said the upgrade by the TCN couldn’t have come at a better time as the capacity of most of the 132KV lines become limited due to time and usage culminating to inability to operate at full capacity.

According to him “The TCN is currently embarking on the upgrade of 132 KV lines from Ikeja West to Ota and this activity is phased into four stages. This is the second stage and TCN is upgrading the 132kv lines with more robust and sophisticated replacements which provide an opportunity to increase power evacuation for improved supply to customers as well as offering excellent conductor capacity which can withstand very high voltage.

“The upgrade which is set to commence on Monday, October 11, 2021, will affect customers within Oregun, Anifowoshe, Ojodu, Magodo, Omole, Oba-Akran, Oke-Ira, Ogba, Omole Phase 1 and parts of Ikeja, between the hours of 8:00am and 6:00pm daily, for eight weeks,” he said.

Kumapayi also noted that IE Technicians will be on standby to provide support wherever technical interventions are required for the duration of the upgrade, especially between the hours of 6pm and 8am when supply will be available to customers.

“Even though this is a TCN project, we owe our customers the duty to inform them of the situation because we interface with them on a daily basis. We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our Network to improve power supply to customers under our network. So we want to appeal to our customers to bear with us as this exercise will be beneficial toward the improvement of power supply in our network,” he said.

The DISCO CTO reiterated the company’s commitment to improve infrastructure and exceptional service to its esteemed customers, noting the company’s investment in facility upgrade and installations across its six Business Unit as part of its mission of providing quality and reliable services to customers.

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

The highly anticipated animated series, Iwájú is set to air on DStv Disney Channel... Continue
Coca Cola, Pepsi, American Cola and all other popular brands in the soft drink... Continue
BY FEMI ONAKANREN Recently, the media space has been agog with different plausible explanations... Continue
The Anambra Internal Revenue Service in conjunction with the Chartered Institute of Taxation of... Continue
ADEDAMOLA KOLEDOYE  Democracy is defined as the government of the people, by the people,... Continue
In what could be described as a shock and dramatic turn out of events,... Continue
MICHAEL AKINOLA    A 42-year old man, Mordi Collins, who allegedly posed as a... Continue
CHRISTIAN ABURIME      “Carve your name on hearts, not tombstones.” – Shannon Alder... Continue
Tension may heighten within the ruling All Progressives Congress, APC, concerning the constitution of... Continue
10 key points from the Central Bank Governor, Dr Yemi Cardoso’s interaction on the... Continue

UBA


Access Bank

Twitter

Sponsored