Lagos State Govt Completes First Phase Of Odo Iya Alaro Bridge Maintenance Ahead Of Schedule

Posted on August 22, 2024

The Lagos State Government has announced the successful completion of the first phase of routine maintenance and rehabilitation work on the Odo lya Alaro Bridge, located in Kosofe Local Government Area.

 

The Special Adviser to the Governor on Infrastructure, Engr. Olufemi Daramola, shared this update during an inspection of the bridge with a team of Lagos State Government officials from the Office of Infrastructure and the Ministry of Transportation.

The rehabilitation work on the bridge is divided into two phases: the Ojota-bound lane and the Yaba/Maryland-bound lane. Daramola expressed satisfaction that the first phase was completed ahead of schedule.

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

While public attention continues to grow around Fawumi Kayode Abiodun (FKA), what sets him... Continue
BY PAUL IYOGHOJIE A 55-year-old suspected stolen goods receiver, Aliyu Idris has been arrested... Continue
The nomination of Joseph Olasunkanmi Tegbe as Minister of Power by President Bola Ahmed... Continue
AFEES ADELABU  ​The August 15, 2026, race for Osun’s Government House has officially moved... Continue
Award-winning singer and songwriter Praiz brought a new level of ambience to the intimate The... Continue
Notable Niger Delta socio-cultural group, the Orashi National Congress, ONC, has issued an open... Continue
MICHAEL AKINOLA A 65-year old man, Femi Bankole, has been arrested and charged in... Continue
CAJETAN DUKE It was Albert Einstein, a German philosopher and scientist, who said that... Continue
MICHAEL AKINOLA Two suspects, Elijah Emmanuel and Tony Oghanetega, who killed a 17-year- old... Continue
KINGSLEY EBERE   On Sunday, 3rd May, 2026, the family and the congregation of... Continue

UBA


Access Bank

Twitter

Sponsored