Lekki Port Faces N2bn Contract Dispute as Engineering Firm Alleges Unlawful Termination

Posted on July 13, 2026

A major contractual dispute has erupted between Ajirit Engineering Logistics Limited and Lekki Port LFTZ Enterprise Limited, with the engineering firm claiming losses exceeding N2 billion following the termination of a dredging and reclamation contract at the port’s Phase 2 expansion project.

Ajirit in a statement issued on Monday through its solicitors, Strict Attorneys, alleged that Lekki Port prematurely terminated a Service Level Agreement signed on March 28, 2025, for the dredging and reclamation of approximately one million cubic metres of sand within the port area.

The company further claimed that it had committed significant financial, technical and human resources to the project and had already completed substantial aspects of the contract before the termination occurred.

Ajirit alleged that it deployed multiple excavators between April and May 2025, excavating about 75,000 cubic metres of material and achieving approximately 90 per cent completion of access channel dredging.

The company also claimed to have delivered more than 80 pipeline units to the site and installed about 840 metres of pipelines, representing 80 per cent completion of pipeline infrastructure.

The firm further stated that a Cutter Suction Dredger was mobilised and deployed to the project site on May 5, 2025, with equipment inspections and test runs conducted in the presence of Lekki Port officials.

However, Ajirit said operations encountered challenging marine conditions, including severe tidal forces that affected equipment stability. While maintained that it initiated recovery and technical remediation efforts and remained ready to complete the project.

The company alleged that despite these efforts, Lekki Port abruptly terminated the contract, denied access to the site and refused to allow continuation of the work, the action it described as a case of “prevention of performance” and argued that established legal principles entitle it to compensation for work already executed and expenses incurred.

The company disclosed that it is currently seeking about N1.26 billion in compensation, while total claims could exceed N2 billion if the matter proceeds to litigation.

Ajirit however said it remains open to an amicable resolution but is prepared to pursue legal remedies, including court action and arbitration, to recover its alleged losses.

All efforts in getting the reactions to the allegations were unfruitful, as messages and calls sent via +86159….4854 and 0708….2693, to Mr. Zong Williams, the Head of Technical department of Lekki Deep Seaport were unanswered and unreplied as at the time of filing this report.

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

DOZIE IKEDIFE JR  Politics is often described as the art of acquiring power. Governance,... Continue
MICHAEL AKINOLA A 38-year-old school teacher, Jackson Odhomi, was on Monday arraigned before a... Continue
EBUKA ONYEKWELU, Ph.D The Government of Anambra State has been ranked high, scoring 100... Continue
A major contractual dispute has erupted between Ajirit Engineering Logistics Limited and Lekki Port... Continue
CYRIACUS IZUEKWE A 24-year-old man, Micheal Abiodun, has been arraigned before an Ikeja Magisterial... Continue
The Executive Chairman of Ogba/Egbema/Ndoni Local Government Area (ONELGA), Sir Dr. Chukwu Shedrack Ogbogu,... Continue
WISDOM ONIEKPAR IKULI  Many young people only know High Chief (Hon.) Dr. Kingsley Kemebradigha... Continue
MICHAEL AKINOLA  The Ogba Magistrate Court in Lagos is set for an unprecedented security... Continue
Dangote Industries Limited has intensified efforts to combat illegal haulage activities involving its trucks... Continue
Fitness entrepreneur and content creator, Jack Manuel Fitness, recently joined the Goodnews Naija Podcast, where... Continue

UBA


Access Bank

Twitter

Sponsored