Lagos-Ibadan Expressway Is 40% Completed

Posted on September 1, 2019

As the federal government prepares for partial closure of the Lagos-Ibadan Expressway on Monday for repairs, the Federal Controller of Works in Lagos, Adedamola Kuti, says the project is still 40 per cent completed.

Kuti told the News Agency of Nigeria (NAN) in Lagos that the project, which began in 2013 and earlier scheduled to end in 2017, would now be completed by 2021/22 because the Muhammadu Buhari administration included some missing features.

He listed the additional features to include underpasses, footbridges, flyovers, toll plazas and road expansion.

Kuti said that the additional features shifted the completion date.

He added that the additional features made the completion level to still be at 40 per cent which it recorded months ago.

On the Ikorodu-Sagamu Road, expected to serve as an alternative route as construction work progresses on Lagos-Ibadan Expressway, Kuti said that the project was about 18 per cent completed.

He, however, added that critical sections of the highway likely to cause gridlock had been stabilised.

“The highway is about 18 per cent completed but I can tell you now for sure that there is great improvement on the road.

“What we did is to, first of all, tackle critical spots that cause traffic, and we are trying to link them up,” he told NAN.

He said that the Ministry of Works and Housing was working at night on some roads to ease gridlock.

“We have been fixing terrible but strategic roads. We are intervening here and there,’’ he said.

He noted that several road projects were abandoned in the past due to funding constraint, compelling the government to seek alternative sources of funding to fix more roads.

“A lot of projects were having difficulties getting appropriate funding but with other sources of funding, life has been brought into one or two of our projects, and that is why you are seeing activities everywhere.

“Lagos-Ibadan Expressway is progressing, Apapa-Oshodi-Ojota-Oworonsoki Expressway Rehabilitation and Reconstruction project is on, and these are the critical roads that bind everybody, especially in Lagos, together,’’ he said.

According to him, contractors are no longer being owed.

“Now, it is open-ended for contractors to collect whatever is the worth of work done in any project,” Kuti concluded.

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest News

African Fashion Week London (AFWL) 2026, held at 8 Northumberland Avenue and the British... Continue
United Bank for Africa Plc, UBA, has informed shareholders and the investing public that... Continue
The Rivers State Governor, His Excellency Sir Siminalayi Fubara, has charged Nigerian judges to... Continue
CYRIACUS IZUEKWE  A 32-year-old man, Amechi Solomon, was arraigned before an Ikeja Magistrate Court... Continue
KINGSLEY EBERE  The District Head of Lailaba and Sarkin Gobir Lailaba in Kebbi State,... Continue
The Glade Crescent Foundation for Youth Empowerment, a philanthropic initiative founded by tech expert... Continue
CYRIACUS IZUEKWE A 23-year-old man, Daniel Essen, was arraigned before a Lagos Magistrate Court... Continue
EBUKA ONYEKWELU, Ph.D The Government of Anambra State has moved to strengthen the Anambra... Continue
ADE BAMIDELE        You may have seen front-page headlines and advertorials claiming... Continue
CYRIACUS IZUEKWE Residents of Ojo, Badagry and Ibeju-Lekki areas of Lagos State are lamenting... Continue

UBA


Access Bank

Twitter

Sponsored